Spanish Fork, UT — The Spanish Fork FitCity Center is full of progress. Each day the building gets closer towards completion this fall.
The construction of the building is split into three areas, A, B, and C. Area A includes the locker rooms and indoor pool area - excluding the competition pool. Area B includes the competition pool, boiler, electrical, and chemical storage. Area C includes the community/senior center, multipurpose gym, fitness area and track, and administrative offices.
Structure Updates
Area A:
- Pool slide footings are complete
- Lazy river footings at entrance completed
- Faux rock ready for color
- Bathroom tiling progressing
- Curtain wall glass installation ongoing
Area B:
- Pool equipment installation ongoing
- Handrail installation has begun
- Bathroom tiling progressing
- Curtain wall glass installation ongoing
Area C:
- Drywall installation is ongoing
- Painting is proceeding
- Handrail installation has started
- Sound panels in gym complete
- Bathroom tiling ongoing
Site Work:
- Portions of the parking lot are paved and painted
- Retention Wall along river trail is being places
- Pump house fascia and soffit has begun
- Pool bridge footing and foundation complete
Timeline Updates
The project is still on track for a late-fall 2025 opening.