Spanish Fork, UT — If you’ve driven by the FitCity Center lately, you’ve probably noticed that a lot has changed! With sod placed along the trail on Main Street, and much of the glass completed along the front facades of the building it almost looks habitable! Nevertheless, there is still much to do with all of the interior finishes to get the building move-in-ready for this fall.
The construction of the building is split into three areas, A, B, and C. Area A includes the locker rooms and indoor pool area - excluding the competition pool. Area B includes the competition pool, boiler, electrical, and chemical storage. Area C includes the community/senior center, multipurpose gym, fitness area and track, and administrative offices.
Structure Updates
Area A:
- Lazy river footings at entrance completed
- Faux rock is ready for colorization
- Tiling at restrooms is nearly completed
- Curtain wall metal trim is being installed
- Pool structures and membrane are progressing
- Wood railings are finalizing
- Pool deck is being poured
Area B:
- Pool equipment installation is ongoing
- Handrail install is in progress
- Restroom tiling is almost completed
- Curtain wall entrance is ongoing
- Pool membrane has been laid
Area C:
- Drywall finishes are ongoing
- Painting is proceeding
- Handrail installation is in progress around track
- Ceiling tiles are being placed
- Lighting and electrical finishes are being installed
- Kitchen tiling to start this week
- Kitchen Hood Installed
Site Work:
- Retention wall along river trail is being placed
- Pump house plumbing and pool equipment in progress
- Lazy river footings are poured
- Site concrete is moving ahead in preparation for asphalt
- Mechanical units are getting ready for start up
Timeline Updates
The project is still on track for a late-fall 2025 opening.