REC CENTER CONSTRUCTION UPDATE - October 2025

October 6, 2025

Spanish Fork, UT — The FitCity Center is entering the final weeks of construction and completing the finishing touches! A lot is happening every day, getting us closer to opening the facility in December.

The construction of the building is split into three areas, A, B, and C. Area A includes the locker rooms and indoor pool area - excluding the competition pool. Area B includes the competition pool, boiler, electrical, and chemical storage. Area C includes the community/senior center, multipurpose gym, fitness area and track, and administrative offices.

Structure Updates

Area A:​

  • Glass installation is ongoing
  • Locker rooms are getting benches and countertops
  • Door installation is ongoing
  • Painting touchup and caulking is ongoing
  • Indoor pools are filled and complete

Area B:​

  • Bathroom finishes ongoing
  • Store front door installation in progress
  • Electrical finishes are ongoing
  • Caulking touchup

Area C:​

  • Roof top unit start up is ongoing
  • Steel and barn wood are progressing
  • Kitchen equipment is installed
  • Concrete flooring is being polished
  • Wood and athletic flooring is ongoing 
  • Carpet is being laid
  • Indoor playground is installed and complete
  • Storefront and doors are progressing
  • Bathroom finishes are ongoing
  • Paint touchup is happening

Site Work:

  • Trail is sealed
  • Pump house plumbing and pool equipment in progress​
  • Slide tour is installed and complete
  • Kiosk is ongoing
  • Pool electrical is ongoing
  • Iron fencing is progressing
  • Parking lot lighting is in progress

Timeline Updates

The project is still on track for a late-fall (November-December) 2025 opening.